Approach Canal
About 82 m approach canal will connect settling basin and gravel trap. Site clearance and excavation works of approach canal has been completed and the construction of approach canal is completed which takes 100 % of total approach canal works. Approach canal alignment has to cross the selang khola.
- Length: 82 meters connecting the settling basin and gravel trap.
- Completion Status: 100% completed (site clearance, excavation, and construction).
- Special Feature: The approach canal crosses Selang Khola.