Balephi Khola · Sindhupalchok, Nepal
Balephi-A Hydropower Project
22.14 MW run-of-river plant, over 90% built
Power sold to NEA under a 30-year agreement
IPO underway: issue manager and underwriter appointed

- Installed Capacity
- 22.14MW
- Annual Energy Output
- 125.3GWh
- Gross Head
- 86m
- Overall Physical Progress
- 90.58%
Moonlight Hydropower Company Limited was set up in 2006 to build the Balephi-A Hydropower Project in Sindhupalchok District. The plant takes water from the Balephi Khola at a 33 m diversion weir, clears the sediment in a settling basin and carries the flow through a 948 m canal and a 2.3 km steel pipe, 3.8 m across. From there the water drops 86 m to a powerhouse with three Francis turbines. At 22.14 MW, the plant is expected to produce about 125 GWh a year, all of it sold to the Nepal Electricity Authority.
- PPA with NEA for the full 22.14 MW
- 90.58% physically complete (August 2026)
- Roads, irrigation and temple protection for local communities
Board of Directors
The People Steering Moonlight
Three directors oversee the company and the construction of Balephi-A.
-

Mr. Kalyan Bikram Neopane
Chairman
More than 12 years in civil construction and hydropower -

Mr. Sudhir Lamichhane
Director
More than 20 years in corporate management -

Mr. Bed Prakash Bista
Director
More than 15 years in corporate management
From the Site
Construction at Balephi-A
-
Headworks and under-sluice on the Balephi Khola
-
Steel pipeline crossing the terraced fields
-
Pipeline and excavator near the surge tank
-
Powerhouse building
Why Balephi-A
A Plant Built to Run for Decades
A run-of-river plant has no fuel bill. Balephi-A’s income is fixed by a long-term tariff agreement with Nepal’s national utility, and its output adds to the dry-season power Nepal needs most.
-
Over 90% Built
The headworks, settling basin, forebay and surge tank are finished. Remaining work is mainly on the penstock, the turbines and generators, and the 33 kV line.
-
A Contracted Buyer
The Nepal Electricity Authority buys the plant’s output under a power purchase agreement that runs for 30 years from commercial operation.
-
Dry-Season Tariff
Rs 8.40 a unit from December to May and Rs 4.80 in the wet months, with 3% yearly escalation on the base rate in the early years.
-
Local Benefits
About 9 km of village roads, an irrigation canal, and protection works for the Mahadev Mandir and a local school.
- 542.65km²
- Catchment Area
- 32.4m³/s
- Design Discharge
- 124.56GWh
- Contracted Energy a Year
- 30yrs
- Power Purchase Agreement
-
Access Road90%
-
Land Acquisition & Compensation95%
-
Hydromechanical Works70%
-
Electromechanical Works70%
-
Transmission Line67%
Site Updates
Structure by Structure
-
01100% completeHeadworks
The weir, intake, under-sluice, spillway and gravel trap are fully constructed at the headworks site.
Read update -
02100% completeApproach Canal
The 82 m approach canal connecting the gravel trap and the settling basin is fully complete.
Read update -
03100% completeSettling Basin
Excavation, the main body, the pond and the hopper wall of the settling basin are complete.
Read update -
0495% completeHeadrace Canal
910 m of the 948 m headrace canal linking the settling basin to the forebay is complete.
Read update -
05100% completeForebay
Site clearance, the bottom slab, side walls and bellmouth installation are fully complete.
Read update -
0670% completeHydromechanical Works
Of the 2,945 m of combined headrace and penstock pipe, about 2,061 m has been rolled and erected.
Read update -
-
0860% completePenstock
Site clearance, excavation and construction of saddle supports and anchor blocks are underway along the penstock alignment.
Read update -
0995% completePowerhouse
The foundation, earth mat, PCC works and superstructure are complete, and finishing works continue. Turbine and generator components, including the draft tube and main inlet valve, are being delivered and installed.
Read update -
1070% completeProtection Works
Stone masonry retaining structures are under construction to protect key project areas.
Read update -
11100% completeSocial Mitigation
About 9 km of local roads, an irrigation canal, and protection works for the Mahadev Mandir and a local school are complete.
Read update -
1280% completeInfrastructure & Site Camp
Site camps, stores, stockyards and fabrication workshops are in place near the headworks and powerhouse.
Read update -
1390% completeAccess Road
About 17 km of access road from Balephi Bazaar to the headworks and powerhouse has been upgraded and protected.
Read update
Contact
Talk to Us
Questions about the project, the share issue or working with us? Use the form or call our office in Kalopul, Kathmandu, Sunday to Friday.
- Phone Number+977-1-4562844
- Email Addressmoonlighthydropower83@gmail.com
- Address LocationKalopul, Kathmandu, Nepal



