One company, one project: the 22.14 MW Balephi-A Hydropower Project in Sindhupalchok, now in its final phase of construction.

Who We Are

Over 90% built on the Balephi Khola.

Moonlight Hydropower Company Limited was set up in 2006 to build the Balephi-A Hydropower Project in Sindhupalchok District. The plant takes water from the Balephi Khola at a 33 m diversion weir, clears the sediment in a settling basin and carries the flow through a 948 m canal and a 2.3 km steel pipe, 3.8 m across. From there the water drops 86 m to a powerhouse with three Francis turbines. At 22.14 MW, the plant is expected to produce about 125 GWh a year, all of it sold to the Nepal Electricity Authority.

  • PPA with NEA for the full 22.14 MW
  • 90.58% physically complete (August 2026)
  • Roads, irrigation and temple protection for local communities
Kalyan Bikram NeopaneChairman, Moonlight Hydropower
Kalyan Bikram Neopane, Chairman

Chairman’s Message

Dear Shareholders and Well-wishers,

Thank you for your interest in Moonlight Hydropower Company Limited.

The Balephi-A Hydropower Project has entered its final stretch. As of August 2026, construction stands at 90.58%. The headworks, settling basin, forebay and surge tank are complete, the powerhouse is nearly finished, and the turbines and generators are being installed. Progress on each part of the work is published on our Construction page.

We are also preparing to welcome new shareholders. Laxmi Sunrise Capital Limited is managing our public share issue, and Jyoti Capital Limited has agreed to underwrite the shares offered to the general public. Once the Securities Board of Nepal approves the issue, shares will be offered first to residents of the project-affected area and to Nepalis working abroad, and then to the general public.

None of this would be possible without the trust of our shareholders and lenders, the support of the people of Balephi, and the hard work of everyone on site. I thank each of you. We will keep this website up to date as Balephi-A moves towards generation.

Kalyan Bikram NeopaneChairman

Investor Relations

The Company

Seeing One Project Through

Moonlight Hydropower was incorporated on 13 July 2006 and became a public limited company on 15 July 2022. It was promoted by people with long experience of building hydropower and roads in Nepal, among them former chairperson Birendra Bahadur Neopane, who has spent around four decades in civil construction.

  • What We Are Building

    A 22.14 MW run-of-river plant using up to 32.4 m³/s of water from the Balephi Khola and 86 m of head. It is expected to generate about 125 GWh a year.

  • Working With the Community

    Alongside the plant we have built about 9 km of local roads and an irrigation canal, protected the Mahadev Mandir and school buildings, and rebuilt a school wall damaged in the 2015 earthquake.

  • 9kmVillage roads built
  • 90.58%Built, August 2026

Related Group

BIG GROUP

Founded by Group Chairman Birendra Bahadur Neopane in 1985, BIG GROUP grew from road and building construction into hydropower in 2007, and today spans clean energy, manufacturing, healthcare, hospitality, construction and technology.

Its hydropower work includes the completed Mai Khola (4.5 MW), Mai Small Cascade (8 MW) and Upper Puwa Khola (3 MW) plants and the 166 MW Super Tamor project in development.

Visit BIG GROUP
1985
Group founded
450MW
Hydropower capacity across the Group
25
Projects delivered or under way
30
Group companies

Milestones

From Licence to Listing

  1. 2006

    Company Incorporated

    13 July 2006

    Moonlight Hydropower Company was registered as a private limited company to develop hydropower in Nepal.

  2. 2012

    Power Purchase Agreement

    30 October 2012

    PPA signed with the Nepal Electricity Authority for the first 10.6 MW of the project.

  3. 2015

    Generation Licence

    19 April 2015

    Generation licence issued for the Balephi-A Hydropower Project.

  4. 2018

    Construction Begins

    2075 B.S.

    Contractors mobilised to the headworks, canal and powerhouse sites.

  5. 2020

    Capacity Raised to 22.14 MW

    28 December 2020

    The PPA was amended to add 11.54 MW, bringing the contracted capacity to 22.14 MW.

  6. 2021

    Financial Closure

    2 July 2021

    Debt and equity financing for the project was secured.

  7. 2022

    Public Limited Company

    15 July 2022

    The company converted to a public limited company, the first step towards offering shares to the public.

  8. 2024

    Issue Manager Appointed

    28 October 2024

    Laxmi Sunrise Capital Limited signed on to manage the initial public offering.

  9. 2025

    Issuer Rating Assigned

    February 2025

    CARE Ratings Nepal assigned the company an issuer rating of CARE-NP BB- (Is).

  10. 2025

    Ratings Reaffirmed

    December 2025

    CARE Ratings Nepal reaffirmed the issuer rating CARE-NP BB- (Is) and the CARE-NP BB- rating on Rs 4,070 million of bank facilities.

  11. 2026

    Construction Passes 90%

    August 2026

    Physical progress reached 90.58%, with the headworks, settling basin, forebay and surge tank complete.

  12. 2026

    Underwriting Agreement

    September 2026

    Jyoti Capital Limited agreed to underwrite the 9,241,426 shares to be offered to the general public.

  13. Next

    Commercial Operation

    To be announced

    Generation will start once the remaining works, testing and grid connection at the Pangtang substation are complete.

Board of Directors

The People Steering Moonlight

  • Mr. Kalyan Bikram Neopane

    Mr. Kalyan Bikram Neopane

    Chairman

    More than 12 years in civil construction and hydropower
  • Mr. Sudhir Lamichhane

    Mr. Sudhir Lamichhane

    Director

    More than 20 years in corporate management
  • Mr. Bed Prakash Bista

    Mr. Bed Prakash Bista

    Director

    More than 15 years in corporate management

Powering Nepal's Progress, Sustainably

Get in Touch With Us

We're here to answer any questions you may have about the Balephi-A Hydropower Project.