Forebay

Right after headrace canal forebay is purposed. Site clearance layout and excavation on forebay bottom slab and side wall construction area is completed and also the  bellmouth has also been installed and the construction of the forebay is 100% completed.

  • Located immediately after the headrace canal.
  • Site clearance, layout, and excavation of the bottom slab and sidewall construction area are completed.
  • Bellmouth Installation: Successfully installed.
  • Completion Status: 100% of the forebay construction is completed.