Headrace Canal

Home PortfolioHeadrace Canal

Headrace Canal

Headrace canal starts at the end of the settling basin and ends at the forebay. The total length of head race canal is 948 m among which 910m is completed . All the construction of headrace canal is  almost completed so 95 % of the work is completed.

  • Starting & Ending Points: Begins at the settling basin and ends at the forebay.
  • Total Length: 948 meters.
  • Completed Work: 910 meters constructed.
  • Current Status: 95% completion, nearing finalization.